The main track work is over for this year. How ever there are still work trains running so one should play attention while crossing tracks!
The reparation of Syrup spur reached a point more than 200 m from the Jokioinen-Humppila road. There is still about 150 m to go before reaching the factory fence. Track laying continues when spring will arrive, but some preparative work and picking up of old rails will be done during winter months.