Renovation of Humppila road railway crossing next to the Jokioinen station is ready. The team of VR-rata Oy working at Minkiö station installed the pre-made rail elements to the crossing and Soraset Oy took care the traffic control and road surfacing. The old crossing element made of 22 kg/m rails has been replaced by one made of 30 kg/m rails and decked with asphalt. The crossing of a bicycle road has an old style concrete decking. With the concrete decking the gaps between the deck and rails could be made more narrow and thus make the crossing more safe for bicycles.